Before work starts, agree in writing how long the finished site is covered for defects, which browsers and devices it must work on, what counts as a defect rather than a change, and how quickly defects are fixed.

Six weeks in, the form goes quiet

A bookkeeping firm launched its new website in late February. Six weeks later, a client mentions that she sent a request through the quote form and heard nothing.

The office manager tries the form: it says thank you, and nothing arrives. On her phone, the services page runs off the edge of the screen.

The web company replies with an estimate: the site was signed off at launch, so the repairs are new work at the hourly rate.

The firm feels it paid for a site that works. The web company feels it delivered one that worked on the day. Both may be right, because the agreement never said.

What the agreement left out

Many website agreements describe the build in detail and stop at launch, with a final payment and a sign-off. They are silent on faults that surface once real visitors arrive.

Some faults were there all along, unnoticed. Others appear because something around the site changed: a browser update, a new phone, a server setting or a staff edit.

Without terms written in advance, each fault turns into a negotiation, held at the moment both sides are least patient.

This is general information about website agreements, not legal advice on any particular contract.

Defect or change

The most useful clause defines the two words. A defect is the site failing to do what the agreed specification says, on the agreed browsers and devices. A change is anything else.

Writing the grey cases down matters more than which way they are settled. Each side can live with a rule it agreed to beforehand.

How long the build is covered

A defect period, sometimes called a warranty period, covers the finished site for a set time after launch. Thirty, sixty or ninety days are common choices.

Start the clock at public launch, not at design approval. Faults show up under real use, and a period that ends before the site goes live covers very little.

A business with a busy season should ask for the period to include it. The weeks the site works hardest are when hidden faults surface.

Naming the browsers and devices

A page that breaks on one phone is a defect only if that phone was in scope. List the browsers and devices the site must work on, and attach the list to the agreement.

For many small businesses that means Internet Explorer 8 and later, current versions of Chrome, Firefox and Safari, recent iPhones and iPads, and the Android phones customers carry.

The existing site's Analytics shows which browsers your visitors actually use; those are the ones worth naming.

A worked example

A family farm near Salmon Arm runs a corn maze from late August to the end of October, with timed tickets sold online and a booking form for school groups.

On its previous site, the busiest Saturday time slots oversold for two weekends running, and the fix arrived mid-season as an invoice for new work.

For last year's new site, the farm settled terms first. The agreement lists the phones and browsers families use, and sets a defect period running from launch to the end of the season.

It treats ticket sales and the school booking form as critical: a fault there is acknowledged within hours and fixed within one working day. Cosmetic faults go into a weekly batch.

Five weeks into the season, the date picker failed on one Android phone. It was reported with a screenshot and fixed under the agreement, with no talk of an invoice.

A request that same week for a pumpkin patch add-on to the tickets was quoted as a change. With the line already drawn on paper, telling one from the other took a single email.

How quickly defects are fixed

Not every defect is urgent. Critical means customers cannot contact you, buy or book; serious means a page is broken on a listed device; minor means it looks wrong but works.

Agree a response time for each level, in working days, and one place to report faults, with a screenshot, the device and the time it happened.

Testing before sign-off

Many disputes trace back to a sign-off given after a quick look. Test together before launch, against the specification, on the listed devices.

Send every form and confirm the message arrives where it should. Load each page with its real content and check it at phone width.

Sign off with a list of known issues attached. Those are then neither defects nor changes, but promises with dates.

After the cover ends

When the defect period ends, the site still needs looking after. Software updates, new browsers and new content all carry some risk of breaking something.

A maintenance agreement, or at least an agreed hourly rate and response time, keeps later fixes from becoming fresh negotiations.

The counter-case

A small fixed-price site may have a short defect period built into its price, and expecting months of free fixes would be unreasonable. Cover takes time, and it is fair to price it.

Some web companies already put clear defect terms in every agreement, and a business working with one has little to add.

And a business that edits the site's code itself, or lets another supplier do so, cannot expect the original builder to answer for the results.

Even so, every build deserves a few written lines on defects. They protect the web company from open-ended demands as much as they protect the client.

Terms to agree before work starts

  1. Write a specification the finished site can be tested against.
  2. List the browsers and devices it must work on.
  3. Define a defect and a change in plain words.
  4. Set the defect period and the day it starts.
  5. Agree response times for critical, serious and minor faults.
  6. Test every form together before sign-off.
  7. Arrange care for after the period ends.

Step three settles most arguments before they begin. Once both sides have agreed what a defect is, a fault becomes a repair to schedule rather than a bill to dispute.

When a fault falls between several suppliers rather than one, naming a lead in each agreement helps, as four suppliers who each blame another shows.


Frequently asked questions

What is a defect period for a website?

A set time after launch, often thirty to ninety days, during which faults that stop the site meeting its agreed specification are fixed without charge.

How is a defect different from a change?

A defect is the site not doing what the agreement specified, on the listed browsers and devices. A change is anything new or different, and it is quoted separately.

When should the defect period start?

At public launch rather than design approval, since most faults appear under real use. A business with a busy season should ask for the period to cover it.

Which browsers and devices should the agreement list?

The ones your visitors use, taken from Analytics. For many businesses that means Internet Explorer 8 and later, current Chrome, Firefox and Safari, iPhones, iPads and common Android phones.

How fast should a broken form be fixed?

A form that stops sending is usually treated as critical, with a response within one working day. Agree the exact times in writing before any work starts.

What happens after the defect period ends?

Fixes are then covered by a maintenance agreement or charged at an agreed rate. Settling that rate and the response time in advance avoids a fresh negotiation.

West Coast Media Solutions Inc. provides web design, web development, hosting, digital marketing, and business consulting to organisations across Canada, drawing on more than twenty-five years in the field.

Website agreement silent on defects?

Send us the agreement or the quote, and we will suggest defect terms that both sides can work with.

Start a Conversation